3D House Rendering

Artesian Modern

5/18/2023

We finished framing (wood and steel) and are now installing windows. The exterior walls of this house is about 70% glass!

8/24/2022

Pouring foundation on 10,000 sqft house. Approximately 370 tons of big rock fly ash concrete mix from Robertson’s being pumped by Alliance Concrete Pumps through a 4″ line.

6/15/2022

Final conceptual 3D rendering approved for construction drawings.